Sponsored Programs Proposal Submission Timeline Requirements


Effective for proposals due to the sponsor after September 15, 2025, the Enterprise for Research, Innovation and Knowledge is implementing a formal Sponsored Programs proposal submission timeline requirement. Following this standard timeline will allow for:

The required proposal components and the deadlines by which they must be provided to Sponsored Programs allows staff to complete their review prior to submission to the sponsor. The deadlines vary depending on whether a proposal is classified as complex or standard.

General requirements

Standard proposals

Proposals not meeting the complex criteria are considered standard proposals, including proposals where Ohio State is not the lead applicant but is a subawardee in another applicant’s proposal. Lead applicants may require subawardee proposal documents before their sponsor deadline. In such cases ERIK’s timeline will be triggered by the date the lead applicant requires the proposal documents from Ohio State. So, for standard proposals due September 15, an intake form must be completed by September 1. 

Complex proposals

Complex proposals require significant time and resources to draft and assemble the administrative, business and technical components of the proposal. Complex proposals:

Internal Deadlines for Proposal Review and Submission

The following items are required by Sponsored Programs before proposals may be submitted to sponsors. Deadlines listed are lead times prior to the day the proposal is due to the sponsor, and items will be due by noon on those days.  For example, if a proposal is due to the sponsor by 5 p.m. Friday the entire standard proposal would be due to Sponsored Programs by noon on Wednesday. Timelines noted are the minimum to meet the requirement. Every effort should be made to notify Sponsored Programs of an intent to submit and provide documents as far in advance as possible.

 

Proposal Items

Standard Proposals

Complex Proposals

PI notification in proposal intake system

2 weeks

3 months

Subaward documents

7 business days

4 weeks

Budget documents when cost share or voluntary reduction of indirects proposed*

6 business days

3 weeks

Final budget and administrative documents

4 business days

2 weeks

Research documents

2 business days

7 business days

ePA-005 routed for approvals*

3 business days

5 business days

Proposal complete/ready for SPO review

2 business days

3 business days

 *If budget includes cost share or a voluntary reduction in indirect costs, budget documents and PA-005 must be submitted at least 6 business days in advance of proposal deadline to allow time for review.

 

Proposal item definitions